Cam Lam – Vinh Hao Component Project under the Eastern North – South Expressway Construction Project in the period of 2017 -2020

Project name : Cam Lam – Vinh Hao Component Project under the Eastern North – South Expressway Construction Project in the period of 2017 -2020
Project Owner : PMU 85
Funding source : State budget
Project location : Khanh Hoa, Ninh Thuan and Binh Thuan Provinces, Vietnam
Description of the Project:
Cam Lam - Vinh Hao Expressway Project has a total length of 78.5km, passing through Khanh Hoa - Ninh Thuan and Binh Thuan provinces. In the first phase, a four-lane expressway was built and it will expanded into a six-lane expressway in the final phase. Design speed ranges from 90km/h - 120km/h. The entire route consisted of 34 bridges, including 23 bridges on the expressway and 11 flyovers; 02 interchanges (Du Long and Phan Rang interchanges); 10 intersections and 2.25km of tunnel through Vung mountain. The project was classified as a traffic works of Grade I, category A project. When completed, the project will help reduce travel time between Ho Chi Minh City and Ninh Thuan from 8 hours to 4 hours, contributing to socio-economic development, tourism and improving people's living standards. Total investment was USD 360 million (equivalent to VND 8,925 billion).
Services provided by Hung Nghiep:
- Topographic, geological and hydrological surveys; survey of construction material quarries; the existing road surface survey; survey of waste disposal areas and locations of concrete mixing plants.
- Survey of the existing structures on the route including road crossings, intersections, power lines, underpasses, canals, culverts and drainage systems;
- Placing site clearance stakes and red-line boundary markers
- Technical design of expresway, bridges and culverts, drainage systems, etc.
- Prepare cost estimates and related reports
- Author supervision.